A Comprehensive Analysis of Principal Contributing Factors to Construction Project Delays: A Multi-stakeholders Perspective on Financial Bottlenecks, Design Revisions, and Coordination Failures in High-rise Development

Authors

  • ADE ASMI Department of Civil Engineering, Universitas Bakrie, Jakarta, Indonesia. Author
  • ANGGA PRABOWO Department of Civil Engineering, Universitas Bakrie, Jakarta, Indonesia. Author
  • AURINO DJAMARIS Department of Management, Universitas Bakrie, Jakarta, Indonesia. Author

DOI:

https://doi.org/10.64137/31079377/IJMSD-V2I2P102

Keywords:

Construction Project Delays, Multi-Stakeholder Perception, Cash Flow Management, Spearman Rank Correlation, Project Risk Mitigation, Building Information Modeling

Abstract

This study investigates the primary factors contributing to schedule deviations in high-rise construction projects, focusing on the interconnected dynamics of financial bottlenecks, technical revisions, and coordination failures. Employing a mixed-methods approach, data are collected from fifty-four industry professionals representing contractors, owners, and consultants through structured questionnaires evaluating thirty-three delay variables. Reliability analysis yields a Cronbach’s Alpha of 0.949, confirming robust instrument consistency. Progress tracking via S-curve analysis identifies a critical deviation of -4.43 between March and May 2021. Spearman Rank correlation reveals a strong positive relationship (r = 0.861) between delayed worker payments and diminished labor productivity. Results indicate that stakeholders perceive delay drivers differently: contractors emphasize coordination gaps, owners highlight financial constraints, and consultants prioritize technical rework. The research transcends traditional risk identification by proposing a role-based mitigation framework that integrates proactive cash flow management, formal change order protocols, and digital communication infrastructure. These findings provide actionable strategies for optimizing time control, enhancing stakeholder alignment, and minimizing schedule deviations in complex residential developments.

References

[1] Project Management Institute (PMI), Guide to the Project Management Body of Knowledge, 7th ed. Pennsylvania: Project Management Institute, 2021.

[2] W. I. Ervianto, Manajemen Proyek Konstruksi (Edisi Revisi), Yogyakarta: Andi, 2018.

[3] M. Sutrisna, J. S. Cooper-Cooke, and B. Goulding, "Investigating delays in Indonesian construction projects: A case study of high-rise building," Int. J. Constr. Supply Chain Manag., vol. 10, no. 1, pp. 20-40, 2020.

[4] A. Santoso and Y. Santosa, "Analisis Faktor-Faktor Penyebab Keterlambatan Proyek Apartemen di Jakarta," Jurnal Teknik Sipil, vol. 18, no. 2, pp. 145-156, 2022.

[5] M. Gunduz and J. Mohammad, "Assessment of delays in main pipelines construction projects," J. Civil Eng. Manag., vol. 26, no. 5, pp. 438–447, 2020.

[6] A. O. Al-Najjar and M. J. Al-Shihabi, "Key factors leading to time overruns in construction projects: A global review," Int. J. Constr. Manag., vol. 23, no. 4, pp. 612-625, 2023.

[7] Y. J. Yap, M. Skitmore, and A. Bridge, "Causes and effects of design change in high-rise buildings: A review," J. Eng. Des. Technol., vol. 19, no. 1, pp. 248–265, 2021.

[8] Y. J.-T.. Zidane and B. Andersen, “The top 10 universal delay factors in construction projects,” International Journal of Managing Projects in Business, vol. 11, no. 3, pp. 650–672, Jul. 2018, doi: https://doi.org/10.1108/ijmpb-05-2017-0052.

[9] S. H. Khahro et al., "Risk Severity Assessment of Delay Factors in High-Rise Building Projects: A Case Study," Appl. Sci., vol. 11, no. 11, p. 5232, 2021.

[10] M. Hossen, S. Kang, and J. Kim, "Construction Schedule Delay Risk Assessment by Using Structural Equation Modeling," Appl. Sci., vol. 11, no. 12, 2021.

[11] N. Widhiawati, I. G. A. Adnyana, and I. Putu, "The Impact of Financial Factors on Construction Project Timelines in Bali," J. Sustain. Constr., vol. 5, no. 1, pp. 12-25, 2021.

[12] R. Rachman, "Manajemen Risiko Keterlambatan Proyek Gedung Bertingkat menggunakan Metode Fishbone," Jurnal Konstruksia, vol. 13, no. 1, pp. 89-102, 2022.

[13] S. Siregar, "Evaluation of Contractor's Financial Performance on Project Schedule during Economic Recovery," Indonesian J. Civil Eng., vol. 10, no. 3, 2023.

[14] F. Ulubeyli, "Financial Problems in Construction Projects: A Systematic Review," J. Financial Manag. Property Constr., vol. 28, no. 2, pp. 180-205, 2023.

[15] K. Al-Mhdawi et al., "Multi-stakeholder perception of delay factors in large-scale infrastructure projects," Buildings, vol. 13, no. 2, p. 450, 2023.

[16] A. S. Al-Emad et al., "Evaluation of Coordination Factors Influencing Construction Success in High-Rise Buildings," J. Manag. Econ., vol. 7, no. 1, 2023.

[17] P. Viles et al., "Assessing the differences in perception of delay factors between owners and contractors," Constr. Econ. Build., vol. 20, no. 2, 2020.

[18] J. B. Singh and R. L. Devi, "Influence of Project Consultant Expertise on Delay Mitigation," J. Archit. Constr., vol. 4, no. 2, pp. 55-67, 2021.

[19] M. A. W. Pratama, "Analisis Hubungan Komunikasi antar Stakeholder terhadap Kinerja Waktu Proyek," Jurnal Infrastruktur, vol. 7, no. 1, pp. 33-45, 2021.

[20] S. Ahmed, P. K. Jha, and N. Kassem, "Construction project delays during and after COVID-19: A comprehensive review," Eng. Constr. Archit. Manag., vol. 29, no. 9, 2022.

[21] L. Liu et al., "The role of Building Information Modeling (BIM) in reducing technical delays: A systematic review," Autom. Constr., vol. 132, 2021.

[22] G. G. J. Prabawa, "Optimization of Labor Productivity to Mitigate Delays in Residential Projects," Civ. Eng. Rev., vol. 4, no. 2, 2022.

[23] B. S. Khoso, "A New Framework for Identifying Non-Excusable Delay Factors," J. Eng. Technol., vol. 40, no. 4, 2021.

[24] H. S. Alawad, "Technical Rework and its Correlation with Project Delay in High-Rise Construction," J. Constr. Eng., vol. 12, no. 3, 2024.

[25] M. S. Faridi, "Impact of Equipment Failure and Maintenance on Construction Schedules," J. Mech. Civil Eng., vol. 19, no. 5, 2022.

[26] Fédération Internationale Des Ingénieurs-Conseils, FIDIC Conditions of contract for construction for building and engineering works designed by the employer: general conditions: guidance for the preparation of particular conditions and annexes: forms of securities : forms of letter of tender, letter of acceptance, contract agreement and dispute adjudication/avoidance agreement, 2nd ed. Geneva: Fidic, 2017.

[27] A. Asmi and A. R. Djamaris, “Project Delay Factor Ranking among Contractor, Client and Project Management Consultant in Construction Industry,” WIDYAKALA: JOURNAL OF PEMBANGUNAN JAYA UNIVERSITY, vol. 8, no. 2, p. 48, Sep. 2021, doi: https://doi.org/10.36262/widyakala.v8i2.389.

[28] Sugiyono, Metode Penelitian Kuantitatif, Kualitatif, dan R&D, Bandung: Alfabeta, 2018.

[29] V. W. Sujarweni, SPSS untuk Penelitian, Yogyakarta: Pustaka Baru Press, 2014.

Downloads

Published

2026-04-08

Issue

Section

Articles

How to Cite

A Comprehensive Analysis of Principal Contributing Factors to Construction Project Delays: A Multi-stakeholders Perspective on Financial Bottlenecks, Design Revisions, and Coordination Failures in High-rise Development. (2026). International Journal of Modern Scientific Discoveries, 2(2), 7-13. https://doi.org/10.64137/31079377/IJMSD-V2I2P102